In short
Numbers marked “our math” are our estimates, not official figures. The notes show the inputs and the steps.
What a transfer is
The city keeps its money in separate funds. A transfer moves money from one fund to another. It is not new money. The water and sewer fund’s yearly payment is on its own page: utility fund overhead payments.
Each transfer in 2025
| From | To | Amount | Reason the audit gives |
|---|---|---|---|
| Main fund | Building projects fund | $5,913,604 | Fund building projects |
| Smaller funds | Building projects fund | $3,230,856 | Growth deals with businesses |
| Water and sewer fund | Main fund | $1,500,000 | Administrative overhead |
| Smaller funds | Debt fund | $1,102,250 | Growth deals with businesses |
| Golf fund | Main fund | $1,000,000 | City projects charged to the golf fund |
| Main fund | Smaller funds | $224,801 | Public art and growth deals |
All amounts are from the audit.1 “Smaller funds” is our plain name for what the audit calls nonmajor funds. “Growth deals” is our name for what the audit calls economic development incentive agreements.
Growth-deal money
Two transfers were for growth deals. Together they come to $4,333,106 (our math).2 One went to building projects. The other went to the fund that pays debt.1
A gap in the audit’s tables
The audit has two tables. The first says the main fund sent out $5,888,405. The second lists $6,138,405 going out of the main fund (our math). The gap is $250,000. That matches a $250,000 transfer out of the building projects fund in the first table. The second table does not list it.3
The other side
- A transfer is not new money. The same dollar leaves one city fund and lands in another.
- Some transfers pay back shared costs. The golf fund’s $1 million was for “City projects allocated to Golf Fund.”1
- What the sources do not show: that any money is missing. The gap is between two tables in the audit.3
Questions to ask
- Why does the second table leave out the transfer from the building projects fund, by the city’s account?
- Which growth deals did this money go to?
- Which city projects were allocated to the golf fund?
Changes to this page
- Nov. 2, 2026: Rewrote the questions to ask so each is open, neutral and addressed to the public body.
- Nov. 2, 2026: Added an other-side section and questions to ask.
- Nov. 2, 2026: New page.
Footnotes
-
City of Leander, Texas, Annual Financial Report for fiscal 2025, Note 7, “Interfund Transfers,” p.52: total transfers $12,971,511. Purposes: Capital Projects Fund from General Fund $5,913,604 “Fund Capital Projects”; Capital Projects Fund from NonMajor Funds $3,230,856 “Economic Development Incentive Agreements”; Debt Service Fund from NonMajor Funds $1,102,250 “Economic Development Incentive Agreements”; NonMajor Funds from General Fund $224,801 “Public Arts Fund & Economic Development Incentive Agreements”; General Fund from Utility Fund $1,500,000 “Administrative Overhead”; General Fund from Golf Fund $1,000,000 “City projects allocated to Golf Fund.” ↩ ↩2 ↩3 ↩4 ↩5 ↩6
-
Our math: $3,230,856 + $1,102,250 = $4,333,106. The first table in Note 7 also shows nonmajor funds transferring out $4,333,106. ↩ ↩2
-
Our math from Note 7, p.52. First table: General Fund transfer out $(5,888,405); Capital Projects Fund transfer out $(250,000). Second table, General Fund as the source: $5,913,604 + $224,801 = $6,138,405. $6,138,405 − $5,888,405 = $250,000. ↩ ↩2