Key facts
The 30-second version
The council approves big city contracts at its meetings. Most land on the consent agenda. That is a list of items the council passes all at once, with one vote. The minutes do not show whether items were discussed before the meeting. Any council member can pull an item off the list to talk about it.
From December 2023 to August 2026, 17 of 21 new contracts worth $1 million or more went through on consent. Every big item we checked passed with no “no” votes.12
How a contract gets bigger
After a contract is signed, the price can change. This is called a change order. Of the change orders we found for $1M+ contracts, all but one went through on consent.1
Recent contracts also let the City Manager approve change orders without the council. Each one can be up to $50,000, and the total up to 25% of the original price.4
Deep dive
| Contract | Original | Latest | Growth |
|---|---|---|---|
| Water meters system (Core & Main) | $9.07M | $11.09M | +22.2% |
| Road repairs FY2025 (Lone Star Paving) | $1.41M | $1.76M | +24.6% |
| RM 2243 reclaimed water line (C.C. Carlton) | $6.97M | $7.81M | +12.1% |
| San Gabriel Pkwy Phase 2 (Patin) | $6.91M | $7.60M | +9.9% |
| Bagdad pump station (Joe Bland) | $19.97M | $20.55M | +2.9% |
| Senior Activity Center (DKC) | $8.78M | $8.84M | +0.6% |
The largest single item was a $97.6 million water-plant contract with Webber Waterworks. It was signed by the regional utility the city shares with neighbors. Leander’s share is 52.4%, or $51.2 million. The council approved it on consent on Nov. 6, 2025.5
Most new awards cite a city bid number, which means the job was put out for competing offers. Two fire engines ($2.2M) were bought through a purchasing co-op, HGACBuy.1
The other side
- The consent agenda lets the council pass routine items in one vote. The minutes do not show any briefings members had before the meeting.
- Any council member can pull an item for debate. One big item was pulled in these years.2
- Change orders can come from added work or site conditions. We did not check the reason for each one. The 10 contracts we tracked grew 7.5%.3 We do not claim anything was done wrong.
Questions to ask
- How does each project’s final cost compare with its first estimate, by the city’s records?
- Where does the council post approved contracts?
Changes to this page
- Nov. 2, 2026: Plainer wording about what the minutes show.
- Nov. 2, 2026: Added questions to ask.
- Nov. 2, 2026: We removed a guess about briefings before council meetings.
- Nov. 2, 2026: We checked every figure against its source. We reworded the other-side points so they stick to what the sources show.
What you can do or watch next
- Read the consent agenda before each council meeting; it is posted a few days ahead.
- You can ask a council member to pull an item so it gets discussed in public.
- Watch change orders on the biggest contracts in the coming year.
What we still don’t know
- Some minutes are scans read by a computer, so a few words can be wrong.
- How each project’s final cost compares with its first estimate, for every project.
Footnotes
-
City Council agendas, Dec. 2023–Aug. 2026, CivicClerk (leandertx.api.civicclerk.com). Dataset: our dataset. ↩ ↩2 ↩3 ↩4 ↩5 ↩6
-
City Council minutes for the same meetings (scanned; read by OCR). On Nov. 1, 2026, we proofread all 65 rows against the OCR text of the minutes: 64 votes matched, each with no “no” votes, and one item (May 2, 2024, item 9) was pulled from consent and heard later. OCR can misread names or numbers, so check the original PDF before quoting a vote. We also compared names and amounts with the scanned pages for May 2, 2024 (DKC, Senior Activity Center) and Nov. 6, 2025 (DKC change order; Webber, $97,619,149, Leander share 52.4%); they matched. ↩ ↩2 ↩3
-
Agendas Jan. 16, 2025; Mar. 6, 2025; May 21, 2026; Aug. 6, 2026 (minutes: approved 7–0). ↩
-
City Council agenda and minutes, Nov. 6, 2025. ↩